Horse Heaven Application
Application Extension Request
The fourth Application Extension Request was approved by the Council at the January 31, 2024 EFSEC Council Meeting. The Extension ends April 30, 2024.
Application Extension Request
Document Title | Document Date | |
---|---|---|
Extension Request | 01/07/2022 | |
Extension Request 2 | 09/27/2022 | |
Extension Request Submitted and Withdrawn | 03/20/2023 | |
Extension Request 3 | 06/12/2023 | |
Extension Request 4 | 01/24/2024 |
Expedited process
Application
Appendix R istemporarily taken down for redactions and will be reuploaded as soon as possible.
Application Original
Updated and Supplemental Reports to the ASC
Updated HH ASC June 2022
Updated ASC
Updated ASC Redline
Note: Some files are large and may take a long time to download.
NOTE: Missing appendices will be uploaded when redactions are complete.
Final ASC
Sept 2023 Layout Changes
Document Title | Document Date | |
---|---|---|
Layout Option 1 | 09/25/2023 | |
Layout Option 2 | 09/25/2023 | |
Scout Clean Energy Letter - Project Update Responding to Adjudication Concerns | 09/25/2023 |
Activities
Federal Activities
Document Title | Document Date | |
---|---|---|
Department of Defense (DoD) Agreement | 11/10/2020 | |
Department of Defense (DoD) Agreement Amended | 01/20/2023 | |
Department of Defense (DoD) Agreement Map | 05/03/2021 |
Copies of the Horse Heaven application can be found at:
Hard Copy:
Energy Facility Site Evaluation Council
621 Woodland Square Loop SW
Lacey, WA, 98504-3172
360-664-1345
Flash Drive:
Mid-Columbia Libraries Mid-Columbia Libraries Mid-Columbia Libraries |
Mid-Columbia Libraries Mid-Columbia Libraries Richland Public Library |
Mid-Columbia Libraries Mid-Columbia Libraries Washington State Library |
*Libraries added for the Final ASC.