Assigned Site Specialist
Zia Ahmed
Goldeneye BESS
Assigned CFE
Yuriy Korol
Applicant:
Goldfinch Energy Storage, LLC
Facility:
Stand-alone 200 MW/800 MWh BESS
Location:
Skagit County
Status:
Under review
Project background
The Applicant proposes to construct and operate the Project in unincorporated Skagit County, Washington (Figure 1 in Attachment A). The Project is a stand-alone 200 MW/800 MWh BESS (Battery Energy Storage System), with related interconnection and ancillary support infrastructure. The Project is located just outside the eastern edge of Sedro-Woolley, off Minkler Road, within the Skagit Valley, less than 1 mile north of the Skagit River.
The Project is located in unincorporated Skagit County, within the Ag-NRL and RRv zones (County 2023). Current land uses in the Project Area include pasture fields, with a small section of scrub/shrub habitat present near the southeastern tip. A portion of the Project Area also contains four existing structures, which the underlying landowner has agreed to demolish as part of Project construction. Land uses surrounding the project area include rural single-family residences, pastureland, and infrastructure. The Project area is bordered on the north by Minkler Road, and is crossed in a roughly north-south direction by Hansen Creek, and electrical transmission lines that connect to the Sedro-Woolley Substation.
The Applicant is considering various specific lithium-ion battery technologies (see Attachment F for sample equipment specifications). Final technology selection will dictate details of the design layout within the Project Area. The preliminary layout accounts for the Project’s generating capacity; however, the precise equipment and layout have not yet been finalized and the Applicant seeks to permit a range of technology options to preserve design flexibility. Therefore, this ASC analyzes the largest anticipated, worst-case Project Area development footprint.
The proposed facility will provide a service to the regional electric grid by receiving energy (charging) from the PSE electric transmission system, storing energy on site, and then later delivering energy (discharging) back to the point of interconnection. Following construction, the proposed use will not create emissions to air, will not require sanitary facilities, and will not require water except to maintain water-efficient and low-impact landscaping design along the project frontage, and to provide a water source for fire protection.
The Project Area was selected by the Applicant for its favorable site suitability characteristics, including proximity to electrical infrastructure, level terrain and opportunities for efficient construction. The Project will have a number of benefits to the local community and Washington state. Construction of the Project will support up to 50 jobs during peak construction and 2 permanent jobs during operations. The Project will also provide Skagit County with additional tax revenue. In addition, construction of this renewable energy resource will help Washington meet its goal of 100 percent clean electricity supply as set forth in the Clean Energy Transformation Act, passed by the Washington legislature in 2019.
Informational Meeting and Land Use Hearing
The recording of the hearings are available here: August 13, 2024 Goldeneye BESS Info Meeting and Land Use Hearing.
The Public Information Meeting and Land Use Consistency Hearing will be hybrid, held in-person and virtually via Microsoft Teams. You may attend the meeting in person at:
-
Sedro-Woolley Community Center
703 Pacific St
Sedro-Woolley, WA 98284
You may attend the meeting virtually via Microsoft Teams, or via phone:
- Meeting link: https://bit.ly/GoldeneyeInfoMtgLUH
- Call-in number: +1 (564)-999-2000, Conference ID: 507869111#
Below please find the documents associated with these meetings.
InfoMeeting
Document Title | Document Date | |
---|---|---|
Goldeneye Informational Meeting and Land Use Hearing Notice | 08/13/2024 | |
Goldeneye Informational Meeting and Land Use Hearing Notice - SPANISH | 08/13/2024 | |
Goldeneye Informational Meeting and Land Use Hearing Agenda | 08/13/2024 | |
EFSEC Process Overview Presentation | 08/13/2024 | |
Goldeneye BESS Tenaska Applicant Presentation | 08/13/2024 | |
Goldeneye BESS TetraTech Land Use Presentation | 08/13/2024 |
Land Use
Document Title | Document Date | |
---|---|---|
Legal Memorandum - In Support of Land Use Consistency | 08/07/2024 | |
Skagit County Planning Land Use Consistency Decision | 08/07/2024 |
Info Meeting and LUH Public Comments
Document Title | Document Date | |
---|---|---|
Info Meeting and LUH Public Comments - Combined | 08/16/2024 |
Government, Tribal, and Agency Comments
Document Title | Document Date | |
---|---|---|
Skagit River System Cooperative Comment | 07/18/2024 | |
Snoqualmie Tribe Comment | 08/06/2024 | |
Squaxin Island Tribe Comment | 08/06/2024 | |
Skagit County Planning and Development Services Comment | 08/13/2024 | |
39th Legislative District Comment | 08/23/2024 | |
Upper Skagit Indian Tribe Comment | 09/09/2024 | |
Skagit County Board of Commissioners Comment | 09/17/2024 | |
Department of Fish and Wildlife Comment | 09/23/2024 | |
City of Sedro-Woolley Comment | 09/27/2024 | |
Sedro-Woolley School District Comment | 09/27/2024 |
General Comments
Document Title | Document Date | |
---|---|---|
Combined Comments 001-050 | 10/08/2024 | |
051 | 08/19/2024 | |
052 | 08/14/2024 | |
053 | 08/27/2024 | |
054 | 08/19/2024 | |
055 | 08/27/2024 | |
056 | 08/16/2024 | |
057 | 09/10/2024 | |
058 | 09/10/2024 | |
059 | 09/10/2024 | |
060 | 09/16/2024 | |
061 | 09/23/2024 | |
062 | 09/27/2024 | |
063 | 10/08/2024 | |
064 | 10/19/2024 | |
065 | 10/27/2024 | |
066 | 10/27/2024 | |
067 | 10/28/2024 | |
068 | 11/14/2024 | |
069 | 11/05/2024 | |
070 | 11/20/2024 | |
071 | 11/25/2024 | |
072 | 10/19/2024 | |
073 | 10/26/2024 |
Council Member Appointment
Document Title | Document Date | |
---|---|---|
Skagit County Board of Commissioners appoints Robby Eckroth | 08/12/2024 |