On August 22, 2025, Governor Ferguson sent a letter directing Council and EFSEC staff to reconsider certain aspects of the draft Site Certification Agreement (SCA) for the Carriger Solar project.
The Governor asked EFSEC to provide the Yakama Nation opportunity to provide input on proposed mitigation measures to protect Traditional Cultural Properties, involving setbacks, screening tools, traffic control plans, and site restoration plans.
The Governor also directed EFSEC to provide the Yakama Nation with an opportunity to review and provide input on a memorandum from the EFSEC Chair to the Council membership describing the Chair and staff’s June 4, 2025, meeting with the Tribal Council.
Governor Ferguson has directed EFSEC to complete these steps and provide his office with a revised draft SCA within 60 days.
EFSEC will work with the Yakama Nation to ensure all steps are complete within the mandated timeline.
All information and documents regarding this project can be found at: www.efsec.wa.gov/energy-facilities/carriger-solar