We received an application for site certification (ASC) and a request for expedited processing for the Ostrea Solar and High Top Solar projects on April 7, 2022. On June 1, 2022, we convened a virtual informational public meeting and land use consistency hearing. In October 2022, our Council determined that the project was consistent with land use and zoning ordinances; and in November, it granted expedited processing.
We issued a mitigated determination of non-significance (MDNS) for the projects on October 1, 2022. After a 14-day public comment period, we issued a revised MDNS on October 28.
Our Council submitted its recommendation to Governor Jay Inslee on February 17, 2023. He issued a decision, approving the projects on April 6, 2023. We issued a revised MDNS in May 2024. The revision corrected a typo in the previous MDNS regarding the mitigation of a certain habitat type.