Cascade Renewable Transmission updated Land Use consistency information comment period

EFSEC is opening this 30-day public comment period to seek input on the recently received land use information before the Council considers the next steps in its land use consistency review.

Start date
Start time
End date
End time

Scope of comment period

About this comment period

EFSEC held public informational and land use consistency hearings for the Project in November 2025. Since those hearings, EFSEC has received additional and revised land use information from the Applicant, including expanded jurisdiction-specific information and revised figures. EFSEC is opening this 30-day public comment period to seek input on the recently received land use information before the Council considers the next steps in its land use consistency review.

A full list of data request materials, including un-updated materials, can be found in this document search

Comments should focus on whether the updated information accurately and completely addresses the proposed Project's consistency and compliance with applicable local comprehensive plans and zoning ordinances. Commenters may also identify information they believe is missing, unclear, or requires further review.

Related documents

See related meeting documents
Cascade Renewable Transmission* - Application review*
Document date
Data Request
Cascade Renewable Transmission* - Application review*
Document date
Data Request
Cascade Renewable Transmission* - Application review*
Document date
Notice
Cascade Renewable Transmission* - Application review*
Document date
Data Request
Cascade Renewable Transmission* - Application review*
Document date
Decision letter