On October 16, 2017, we received an application for site certification to develop, construct, and operate the Columbia Solar projects spanning five separate solar array sites.
On January 26, 2018, TUUSSOO Energy, LLC, submitted an updated application.
Description
On October 16, 2017, we received an application for site certification to develop, construct, and operate the Columbia Solar projects spanning five solar array sites. We convened an informational public meeting held at the Kittitas Valley Event Center Armory on December 12, 2017.
On January 26, 2018, TUUSSOO Energy, LLC, submitted an updated application. On February 12, 2018, the applicant requested an extension of our Council's timeline for determining the project's eligibility for expedited permitting until April 2018.
On April 17, 2018, our Council granted TUUSSO Energy's request for expedited processing.