Pre-application
Summary
In April 2022, we received draft application materials from Innergex Renewable Development USA, LLC, and provided the prospective applicant with comments and feedback.
Related document
No documents found.
We’ve updated our website to improve your experience. If you need help, contact our web team at websitehelp@efsec.wa.gov.
A facility goes through five different stages. Click on one of the stages before to learn more about our siting process.
In April 2022, we received draft application materials from Innergex Renewable Development USA, LLC, and provided the prospective applicant with comments and feedback.
No documents found.
On May 6, 2022, we received an Application for Site Certification (ASC) from Innergex Renewable Development USA, LLC, proposing the construction of the Wautoma Solar project.
The applicant updated their ASC on August 23, 2024, and submitted a final ASC on October 9, 2024. The applicant filed application extension requests in June 2023, October 2023, and June 2024.
On May 6, 2022, we received an Application for Site Certification (ASC) from Innergex Renewable Development USA, LLC, proposing the construction of the Wautoma Solar project.
We held an informational public meeting virtually on August 8, 2022.
The applicant updated the ASC twice, submitting a revised ASC on August 23, 2024, and a final ASC on October 9, 2024.
The applicant filed three application extension requests in June 2023, October 2023, and June 2024.
No documents found.