Site restoration
Summary
In 2003, Energy Northwest, the U.S. Department of Energy - Richland Office, the Bonneville Power Administration, and the State of Washington agreed on and signed the Four-Party Agreement for the WNP-1/4 site restoration and funding plan.
Description
The agreement adopted a Level 3D restoration plan that included investigating reuse opportunities for the facilities and delaying major site restoration activities to allow for the growth of restoration funds.
The restoration plan includes two restoration phases, near term and long term. The near-term restoration phase occurred within 24 months of the approval of the Level 3D restoration plan focused on health, safety, and environmental protection. Long-term restoration to remove the remainder of the structures and restore the site was scheduled to begin in 23 years (2026) and be completed within 26 years (2029).
Related document
No documents found.